Mathematics Standard • Year 12 • Module 6 • Lesson 10

Cost-Time Trade-offs — Skill Drill

Build fluency in calculating cost slopes, ranking activities for crashing, and finding the minimum total cost duration when indirect costs decline with time.

Build · Skill Drill

1. Quick recall

Answer each question in the space provided. 1 mark each

Q1.1 Cost slope formula: Cost slope = (Crash cost − ____________) ÷ (____________ − Crash time).

Q1.2 When choosing which activity to crash first, you prioritise the activity with the (highest / lowest) cost slope: ____________.

Q1.3 If indirect costs are zero, the optimal project duration is the ____________ duration (no crashing).

Stuck? Revisit lesson § Cost Slope and § Optimal Duration.

2. Worked example — cost slope and one-day crash decision

Each step explains exactly what to calculate and why.

Problem. Activity Z: normal 10 days at $5,000; crash 7 days at $6,200. (a) Calculate the cost slope. (b) If indirect cost is $500/day, is it worth crashing Z by 1 day?

Step 1 — Apply the cost slope formula.

Slope = ($6,200 − $5,000) ÷ (10 − 7) = $1,200 ÷ 3 = $400 per day saved.

Reason: the slope is rise over run — extra direct cost divided by days saved.

Step 2 — Compare to indirect saving per day.

Indirect saving per day = $500. Crash cost per day = $400.

Reason: crashing makes sense whenever direct cost added < indirect cost saved.

Step 3 — Net change per day saved.

Net saving = $500 − $400 = $100/day.

Conclusion. Yes — crash Z by 1 day. The project saves $100 net per day of crashing. Keep crashing until you hit Z's crash limit (3 days max) or indirect cost drops below the slope.

3. Faded example — fill in the missing steps

Activity W: normal 8 days at $3,000; crash 6 days at $3,800. Indirect cost = $250/day. Fill in each blank line. 4 marks

Step 1 — Cost slope:

Slope = ($3,800 − $____) ÷ (____ − 6) = $____ ÷ ____ = $____ per day.

Step 2 — Compare to indirect saving:

Crash cost per day = $____. Indirect saving = $____.

Step 3 — Is crashing worthwhile?

Net per day = $____ − $____ = $____.

Conclusion. Crash W: (Yes / No, choose one) ____________. Net change for 2 days of crashing = $____.

Stuck? Revisit lesson § Worked Example — slope = (extra cost) ÷ (days saved).

4. Graduated practice — Cost-slope skills

Foundation — single-activity slopes (4 questions)

QProblemAnswer
4.1 1Normal 10 days $4,000; crash 8 days $4,600. Cost slope?
4.2 1Normal 6 days $2,000; crash 4 days $2,800. Cost slope?
4.3 1Activity X cost slope = $300/day; indirect = $250/day. Worth crashing? (Yes / No)
4.4 1Activity Y cost slope = $200/day; indirect = $400/day. Worth crashing? (Yes / No)

Standard — multi-activity ranking (6 questions)

Show each slope, then state which activity to crash first.

4.5 Activities A (normal 7, crash 5, +$800) and B (normal 5, crash 4, +$600). Calculate both slopes and state which is cheaper to crash.    2 marks

4.6 Three activities: P (slope $300/day), Q (slope $250/day), R (slope $200/day). Rank them in the order they should be crashed first.    2 marks

4.7 Project normal 18 days at $12,000. Indirect $400/day. Activity A slope $500/day, max 2-day crash. Calculate total cost at 18 days, then total cost if A is crashed by 2 days.    3 marks

4.8 Project normal 20 days $10,000. Indirect $300/day. Activity X slope $400/day, max 3 days. Activity Y slope $250/day, max 2 days. Reduce to 16 days at minimum cost. State which crashes and the total cost.    3 marks

4.9 Project normal cost $8,000. Indirect $500/day. Activity Z has slope $300/day. How many days should Z be crashed if max crash is 4 days? Justify in one sentence.    2 marks

4.10 A penalty clause adds $1,000 for every day the project runs past day 15. The project's normal duration is 17 days. Cost slope of the cheapest critical activity is $400/day. Should the manager crash to day 15? Show working.    2 marks

Extension — find the optimum (2 questions)

4.11 Project normal 22 days $15,000. Indirect $500/day. A: slope $500/day max 2 days. B: slope $800/day max 1 day. C: slope $600/day max 1 day. Find the optimal duration and minimum total cost. Show your work in a small table.    3 marks

4.12 A project has a curve of total cost vs duration: it drops from 25 days (high indirect) down to a minimum around 21 days, then rises again as crashing becomes expensive. Explain in 2 sentences what the rising portion represents and when you would stop crashing.    3 marks

Stuck on 4.11? Crash cheapest first (A); compare total cost at 22, 21, 20, 19, 18 days; pick the minimum.

5. Self-check the easy 3

Tick the first three once you've checked your method works.

How did this worksheet feel?

What I'll revisit before next class:

Answers — Do not peek before attempting

Q1.1 — Slope formula

Slope = (Crash cost − Normal cost) ÷ (Normal time − Crash time).

Q1.2 — Crash priority

Lowest slope first (cheapest per day saved).

Q1.3 — Zero indirect costs

Normal duration — without indirect costs there is no financial reason to crash.

Q3 — Faded example

Step 1: Slope = ($3,800 − $3,000) ÷ (8 − 6) = $800 ÷ 2 = $400 per day.
Step 2: Crash cost/day = $400. Indirect saving = $250.
Step 3: Net = $250 − $400 = −$150/day (loses money).
Conclusion: No, don't crash. 2-day crash would cost net = 2 × −$150 = −$300 (loss of $300).

Q4.1 — Slope

($4,600 − $4,000) ÷ (10 − 8) = $600 ÷ 2 = $300/day.

Q4.2 — Slope

($2,800 − $2,000) ÷ (6 − 4) = $800 ÷ 2 = $400/day.

Q4.3 — Crash decision X

Slope $300 > indirect $250: crashing costs more than it saves. No.

Q4.4 — Crash decision Y

Slope $200 < indirect $400: crashing saves $200 net per day. Yes.

Q4.5 — A vs B

A: $800 ÷ 2 = $400/day. B: $600 ÷ 1 = $600/day. A is cheaper to crash.

Q4.6 — Rank crash order

Lowest first: R ($200), Q ($250), P ($300).

Q4.7 — 18-day project + 2-day crash

At 18 days: $12,000 + 18 × $400 = $12,000 + $7,200 = $19,200.
Crash A by 2: extra = 2 × $500 = $1,000. Duration = 16. Indirect = 16 × $400 = $6,400. Total = $12,000 + $1,000 + $6,400 = $19,400.
Net change: $19,400 − $19,200 = +$200 (worse). Don't crash.

Q4.8 — Reduce 20 → 16 (4 days)

Y is cheaper ($250/day) vs X ($400/day). Y max = 2 days. So crash Y by 2 days ($500), then X by 2 days ($800).
Total crash cost = $500 + $800 = $1,300.
Indirect at 16 days = 16 × $300 = $4,800.
Total at 16 days = $10,000 + $1,300 + $4,800 = $16,100.

Q4.9 — Z slope $300, indirect $500

Net saving per day = $500 − $300 = $200/day. Worth crashing for all 4 days. Crash Z by 4 days (its maximum). Saves 4 × $200 = $800 net.

Q4.10 — Penalty clause

Without crashing: project runs 17 days. Penalty = 2 days × $1,000 = $2,000.
Crash to day 15 (2 days): cost = 2 × $400 = $800. Penalty = $0.
Saving = $2,000 − $800 = $1,200. Yes — crash to day 15.

Q4.11 — Optimal duration

Crash order (cheapest first): A ($500), C ($600), B ($800). All slopes > indirect of $500 means crashing never saves (slope ≥ $500). Crash A: cost $500/day, indirect saving $500/day, net $0. Break-even.
Table:
Duration 22: total = $15,000 + 22 × $500 = $26,000.
Crash A 1 day → 21: $15,000 + $500 + 21×$500 = $26,000 (same).
Crash A 2 days → 20: $15,000 + $1,000 + 20×$500 = $26,000.
Crash A 2 + C 1 → 19: $15,000 + $1,000 + $600 + 19×$500 = $26,100 (worse).
Optimal duration = 20, 21 or 22 days, total cost = $26,000 (any duration from 22 down to 20 is equally good; pick 20 for fastest delivery at no extra cost).

Q4.12 — Cost curve rising portion

The rising portion shows where crash costs exceed indirect savings — each extra day saved costs more than the saving. Stop crashing at the lowest point of the curve: when the next-cheapest crash slope > indirect cost per day.