Mathematics Standard • Year 12 • Module 6 • Lesson 9

Scheduling with Constraints — Past-Paper Style

Practise HSC Mathematics Standard 2-style writing on lag, lead and resource constraints — multi-mark short answers and one structured extended response.

Master · Past-Paper Style

1. Short-answer questions

1.1 A network has: A(3,−), B(4, A lag 2), C(2, B). Compute ES and EF for each activity and state the project duration.    3 marks    Band 3

1.2 A network has: A(5,−), B(3, A), C(4, A lead 2), D(2, B and C). (a) Compute ES and EF for all four activities. (b) State the project duration. (c) On which days do A and C overlap?    4 marks    Band 3-4

1.3 A renovation requires Paint (3 days), then a 2-day drying lag, then Hang fixtures (1 day). A separate Inspection (1 day) is a successor of Hang fixtures with NO lead. The builder claims the lag can be removed by using fast-drying paint, saving 2 days.
(a) State the project duration with the 2-day lag.
(b) State the project duration if the lag is removed.
(c) In one sentence, explain whether removing a lag is the same as "crashing" an activity.    4 marks    Band 4

Stuck on 1.3(c)? Crashing adds resources to an activity; removing a lag uses a different material or process.

2. Extended response

2.1 A regional NSW developer is building a small medical centre. The activity network has:

Site prep (Sp): 3 days, no predecessor

Slab pour (Sl): 2 days, predecessor Sp

Cure (lag of 4 days after Sl)

Frame (F): 5 days, starts after cure

Plumbing rough (P): 3 days, predecessor F

Electrical rough (E): 3 days, predecessor F with LEAD 1 day (E starts 1 day before F finishes)

Final fitout (Fit): 2 days, predecessors P and E

(a) Compute ES and EF for each activity, treating the cure as a 4-day lag.
(b) Identify whether E and F overlap, and if so, by how many days.
(c) State the project duration and identify the critical path. The developer asks: "If we used quick-cure concrete to drop the lag to 2 days, would this shorten the project, and by how much?" Provide the new duration and write a clear conclusion sentence.    7 marks    Band 5-6

Explicit marking criteria

Part (a) — 3 marks

1 mark — Sp, Sl, F correctly computed including the 4-day curing lag between Sl and F.

1 mark — P correctly computed.

1 mark — E correctly computed using the 1-day LEAD (E starts 1 day before F finishes), and Fit computed using max of EF(P), EF(E).

Part (b) — 1 mark

1 mark — overlap of E and F correctly identified as 1 day (the lead).

Part (c) — 3 marks

1 mark — original duration correctly stated.

1 mark — new duration with 2-day cure correctly computed (saving 2 days).

1 mark — explicit conclusion sentence stating the project shortens by 2 days, naming both old and new totals.

Your response:

Stuck on (c)? Recompute Sp + Sl + (lag) + F + P + Fit. Compare lag = 4 vs lag = 2.

How did this worksheet feel?

What I'll revisit before next class:

Answers — sample responses + marking notes

1.1 — Lag in a small chain (3 marks)

Sample response. A: ES = 0, EF = 3. B: ES = 3 + 2 = 5, EF = 5 + 4 = 9. C: ES = 9, EF = 9 + 2 = 11. Duration = 11 days.

Marking notes. 1 mark — A. 1 mark — B with lag applied correctly (ES = EF(A) + lag). 1 mark — C and duration.

1.2 — Lead and merge (4 marks)

(a) A: 0→5. B: 5→8. C: ES = 5 − 2 = 3, EF = 3 + 4 = 7. D: ES = max(8, 7) = 8, EF = 10.

(b) Duration = 10 days.

(c) A runs 0–5; C runs 3–7. Overlap on days 3 to 5 (2 days).

Marking notes. (a) 1 mark — A, B. 1 mark — C with lead. 1 mark — D merge. (b) 1 mark — duration and overlap stated correctly.

1.3 — Lag vs crashing (4 marks)

(a) Paint 0→3. Lag 2 (wait until day 5). Hang fixtures 5→6. Inspection 6→7. Duration = 7 days.

(b) Lag removed: Paint 0→3. Hang fixtures 3→4. Inspection 4→5. Duration = 5 days. (Saves 2 days.)

(c) No — removing a lag is not the same as crashing. Crashing speeds up an activity using extra resources; removing a lag eliminates a mandatory waiting period (here, by switching to a fast-drying material). They both reduce duration but through different mechanisms.

Marking notes. (a) 1 mark — duration 7. (b) 1 mark — duration 5. (c) 2 marks — explains "remove lag = change process / material" vs "crash = add resources to existing activity".

2.1 — Medical centre (7 marks): sample Band-6 response with annotations

Sample Band-6 response.

(a) ES and EF for each activity.

Sp: ES=0, EF=3.
Sl: ES=3, EF=5.
Cure lag = 4 days, so F cannot start until day 5 + 4 = 9.
F: ES=9, EF=14. [Sp, Sl, F including lag — 1 mark]
P: ES=EF(F)=14, EF=14+3=17. [P — 1 mark]
E with lead 1: ES=EF(F) − 1 = 14 − 1 = 13. EF=13+3=16.
Fit: ES = max(EF(P), EF(E)) = max(17, 16) = 17. EF=17+2=19. [E with lead + Fit merge — 1 mark]

(b) Overlap of E and F.

E starts on day 13 (during F, which runs 9–14). E and F overlap on day 13 to day 14 — overlap = 1 day. [1 mark]

(c) Critical path, original duration, and effect of shorter cure.

Original duration = 19 days. Critical path is Sp → Sl → (cure lag) → F → P → Fit. [1 mark — original duration]
With 2-day cure (lag = 2 instead of 4):
Sp: 0→3. Sl: 3→5. F starts at 5 + 2 = 7, ends at 12. P: 12→15. E (lead 1): 11→14. Fit: max(15, 14) = 15 → 17.
New duration = 17 days. Saves 19 − 17 = 2 days. [1 mark — correct new duration]

Conclusion: Using quick-cure concrete shortens the project from 19 days to 17 days — a saving of 2 days. The reduction equals the change in the curing lag (4 → 2) because the lag sits on the critical path. [1 mark — explicit conclusion with both totals named]

Total: 7/7.

Band descriptors for marker.

Band 3: Computes Sp, Sl, F but forgets the 4-day lag, getting an undershoot for the duration. ≈ 3 marks.

Band 4: Lag applied correctly; lead missed (E treated as starting at EF(F)); duration computed but new duration not attempted. ≈ 5 marks.

Band 5: Full forward scan with lag and lead correct; original and new duration computed; conclusion missing or vague. ≈ 6 marks.

Band 6: Complete forward scan, overlap of 1 day stated, both durations (19 and 17) explicitly named with a clear concluding sentence about the 2-day saving. 7/7.