Year 12 Maths Standard Checkpoint 2 ~25 min

Checkpoint 2: Advanced Scheduling

Covers Lessons 7โ€“12: Gantt charts, multiple critical paths, scheduling constraints, cost-time trade-offs, and mixed project problems.

๐Ÿ
Know

Key Facts

  • Gantt chart conventions
  • Multiple critical paths
  • Crash cost slopes
Understand

Concepts

  • Resource levelling
  • Lags and leads
  • Optimal duration
Can Do

Skills

  • Draw Gantt charts
  • Analyse multiple paths
  • Solve mixed problems

Multiple Choice

MC

Revision Multiple Choice

10 questions drawn from Lessons 7โ€“12

Short Answer

๐Ÿ“

Extended Questions

ApplyBand 4

1. A project has: A(3,-), B(4,A), C(2,A), D(5,B), E(5,C), F(2,D,E). (a) Find all critical paths. (b) If D's duration increases to 6, what happens? (c) Draw a Gantt chart showing both paths. (d) Crash D by 1 ($500) and E by 1 ($400). New duration and cost? 5 MARKS

Answer in your workbook
AnalyseBand 5

2. (a) Explain why a Gantt chart is better than an AOA network for presenting a project schedule to a client. (b) A project has two critical paths that share no activities. You have a budget to crash one activity on each path by 1 day. A shared start activity could be crashed by 1 day for the same cost as two separate crashes. Why is the shared crash better? (c) What is the difference between a lag and a lead? 3 MARKS

Answer in your workbook

Comprehensive Answers

โ–ผ

Short Answer Model Answers

Q1 (5 marks): (a) Path correct [1]. (b) Effect [1]. (c) Gantt [1.5]. (d) Cost [1.5].

Q2 (3 marks): (a) Explanation [1]. (b) Reason [1]. (c) Difference [1].