Year 12 Maths Standard Checkpoint 1 ~25 min

Checkpoint 1: Project Networks Fundamentals

Covers Lessons 1โ€“6: project networks, precedence tables, AOA diagrams, forward and backward scans, critical path, float, crashing and resource allocation.

๐Ÿ
Know

Key Facts

  • Network terminology
  • Scan procedures
  • Float formula
Understand

Concepts

  • Critical path meaning
  • Dummy activities
  • Cost-time trade-offs
Can Do

Skills

  • Build and draw networks
  • Calculate ES, EF, LS, LF
  • Identify critical paths

Multiple Choice

MC

Revision Multiple Choice

10 questions drawn from Lessons 1โ€“6

Short Answer

๐Ÿ“

Extended Questions

ApplyBand 4

1. A project has activities: A(4,-), B(3,A), C(2,A), D(5,B), E(3,C), F(2,D,E). (a) Draw the AOA network. (b) Perform forward and backward scans. (c) Find the critical path and project duration. (d) Calculate float for each non-critical activity. 4 MARKS

Answer in your workbook
AnalyseBand 5

2. (a) Explain why a dummy activity has duration 0. (b) A critical activity can be crashed from 8 days to 5 days at a cost of $1500. A non-critical activity with float 4 days can be crashed from 6 days to 4 days at $800. The project must finish 2 days earlier. Which activities should be crashed and what is the minimum extra cost? (c) After crashing, why must you recalculate the critical path? 3 MARKS

Answer in your workbook

Comprehensive Answers

โ–ผ

Short Answer Model Answers

Q1 (4 marks): (a) Network [0.5]. (b) Scans [1.5]. (c) Path and duration [1]. (d) Floats [1].

Q2 (3 marks): (a) Explanation [1]. (b) Choice and cost [1]. (c) Reason [1].